| 
General Description of Construction
Line Items
Mobilization
Before the work can progress, a golf course
builder must mobilize the necessary workers, equipment and
supplies required to construct a course. Local permits and
fees have to be paid prior to beginning construction. Mobilization
costs will vary based on many factors, some of which include
the cost of local housing, location of the site and the time
schedule of when the work is to be performed.
[ Back ]
Layout
and Staking
The owner is responsible for the initial staking
of trees, landing areas and green locations per the golf course
architect’s staking plan. In addition to these initial
points, benchmark elevations during construction are required
throughout the work area for use by the golf course builder.
The builder will identify all golf course features and elevations
for construction using these established control points, and
is responsible for maintaining all of these points. Cost will
vary due to the severity of the site, vegetative cover and
design complexity.
[ Back ]
Erosion
Control
Due to the rules of different government agencies,
the control of erosion on construction sites can vary. Erosion
control requirements can include silt fencing, hay bales,
silt basins and temporary grassing. Types of soil, severity
of topography, proximity of water features and needs of the
surrounding areas will help determine the type of erosion
protection needed.
[ Back ]
Clearing
The amount of clearing necessary is directly
related to the site’s vegetative cover. The size and
marketability of trees and the topography of the site will
impact clearing costs. Local rules and regulations determine
the method of clearing. Burning is allowed in some instances.
In other areas, vegetation will need to be chipped or hauled
off site. In addition to removing vegetation, clearing also
entails the removal of stumps and roots from the soil.
[ Back ]
Selective
Clearing
After the golf course is cleared, the golf course
architect will require additional selective clearing along
the sides of the fairways. This work will require the use
of small machines or may require manual labor. The material
must be burned, hauled away or chipped, depending on local
regulations.
[ Back ]
On-site
Topsoil
If suitable topsoil is available on site, it
will be removed, stored and redistributed at a later point
during construction. In areas where the golf course is constructed
on sand or other suitable soil, the need for stripping isn't
necessary. The topsoil must be clean of roots and stones,
and be of the quality and quantity necessary for planting.
[ Back ]
Off-site
Topsoil
On sites where topsoil is minimal or non-existent,
the soil must be obtained from other sources. The cost would
include the purchase, hauling and spreading of the topsoil.
[ Back ]
Excavation:
Conventional
In order to construct the golf course, excavation
is required to fill or cut areas necessary to meet the golf
course architect’s design requirements. The volume of
work is based on the severity of the site and the golf course
architect’s requirements. The cost of the work is based
on haul distances and types of soil. The work is performed
utilizing trucks and/or scrapers.
[ Back ]
Excavation:
Topload
In some areas, it might be necessary to load
trucks and scrapers using draglines and/or excavators. This
is a much slower procedure than conventional excavation, and
requires additional equipment. This method is also necessary
where soil conditions do not allow conventional methods, such
as lake excavation and long hauls.
[ Back ]
Excavation:
Rocks
When rock is present in the excavation areas,
additional cost might be incurred. If the materials can be
ripped and hauled by conventional means, it is possible that
those added expenses can be avoided. However, if the rock
has to be blasted and removed, there’s little that can
be done to dodge those costs. Additional costs might also
be faced for rock excavation for storm drainage, irrigation
and features construction.
[ Back ]
Rough
Shaping
As the cuts and fills are made with the excavation
process, the golf course builder will contour the course.
This shaping will be performed according to the designer’s
plans and field instructions. The work is performed prior
to the installation of drainage and irrigation systems. The
cost will be based on the complexity of the design and soil
conditions.
[ Back ]
Storm
Drainage
Storm drainage is defined as the drainage system
necessary for moving offsite water through the golf course
and course drainage that exceeds six-inch diameter pipe. The
storm drainage includes outfall structure, catch basins and
any other structures that might be required. The owner’s
engineer commonly designs storm drainage.
[ Back ]
Golf
Drainage
As the golf course is shaped, drainage swales
and small catchments will be developed for golf course playability
and surface drainage. These swales and depressions will require
small field drainage, which will include perforated drains
and small catch basins. The golf drainage will either be connected
to the storm drainage or discharged into other water features
or sumps.
[ Back ]
Irrigation/Pump
Station
The cost of irrigation systems will vary greatly
based on things like the layout of the golf course, terrain,
available water for usage, the amount of coverage, and level
of maintenance. A single row irrigation system may be used
in public play facilities with limited-construction budgets.
In a real estate project where maintained grass is critical,
the area of coverage may be property line to property line
(wall to wall). In general, if water is to be strictly managed,
more complex irrigation controls and a greater number of heads
might be required.
The size of the irrigation pump station will
be based on water demand, course elevation changes and pump
location. The owner will be responsible for furnishing electrical
power to the pumps and also enclosing the pump in a building.
[ Back ]
Greens
The construction of the green involves the installation
of several items necessary for proper functioning of the putting
surface. In this type of construction, the putting surface
is made up of the following layers: a drain field is installed
in a herringbone design in trenches with gravel, a four-inch
layer of approved gravel is installed over the drain field,
then a mixture of sand and peat is installed over the gravel
layer to a compacted depth of 12 inches. Cost of greens construction
will vary based on availability of approved materials.
[ Back ]
Tees
The area of the tees are shaped and graded to
allow for surface drainage. The tees on a golf course may
be built with native materials, if acceptable, such as on-site
sand. Other sites may require the tee surface to be constructed
using the same sand-peat mixture used on the greens. If this
is required, a minimum depth of four inches of mixture is
required. Where soil conditions don't allow for proper drainage,
perforated drains piped with gravel may be required in the
tees.
[ Back ]
Bunkers
Bunkers (sand traps) will be identified and
shaped according to the golf course architect’s direction.
Although the initial work can by done by machine, manual labor
will be required to complete the bunkers to the architect’s
intended design. In addition to the shaping of the bunkers,
drainage will be required. Prior to opening the golf course,
approved bunker sand will be installed to a depth of four
to six inches. This work will also require manual labor. Labor,
sand and the requirements of the design will ultimately determine
the cost of bunkers.
[ Back ]
Bridges
Although large pipes are sometimes used for
crossings, bridges may be necessary in some instances because
of wetland or elevation changes. The owner’s engineer
should approve bridge designs. The bridges should have a minimum
of 10 feet and support the weight of a small dump truck. Bridges
can be prefabricated or built on site based on the owner’s
requirements and budget.
[ Back ]
Bulkheading
Bulkheading might be necessary because of topography
or as an aesthetic element of the golf course design. The
bulkheading can be of many different materials. Plank walls,
railroad ties, piles, bricks and stone have all been used
for constructing bulkheads. Generally, bulkheads are used
around tees and greens and to protect contours, such as lake
banks, from erosion.
[ Back ]
Cart
Paths
Cart paths have been constructed using concrete
or asphalt. Paths can be partial or full-length with widths
varying from six to 12 feet. Typically cart paths are curbed
at the tees and greens to prevent encroachment from golfers.
[ Back ]
Fine
Grading
After the underground parts of the course have
been installed and all the features contoured, the course
must be graded so all the items are related, the golf course
architect's requirements are met, and all surface drainage
is incorporated into the overall requirements. During this
phase of work, the golf course architect can make minor adjustments
to the design contouring where necessary to reflect the design
concept.
[ Back ]
Seedbed
Preparation
After the golf course is fine graded, the surface
of the golf course is prepared for seeding, sod laying or
sprigging. If the site has rock and/or debris within the topsoil,
the area will require rock picking. If necessary, soil amendments
will be added to the seedbed.
[ Back ]
Grassing:
Seed or Sprigs
Relative to the climate and altitude, the golf
course might be seeded with bluegrass, fescue, bent grass
or rye grass, or sprigged or seeded with Bermuda grass. This
operation includes machine planting in fairways and roughs,
and hand planting on the tees and greens. Greens may require
fumigation prior to grassing.
[ Back ]
Grassing:
Sod
Sod will be used in areas to protect detail
shaping and to limit weed contamination. Slopes around tees
and greens may be sodden and a strip may be placed around
the tee and green surfaces to define edges. In addition to
these locations, bunkers will be sodden to stabilize and maintain
the approved contouring. It is generally necessary to sod
around drain inlets to prevent the drain lines from clogging.
[ Back ]
Bonding
If you require a bond for your project, the
cost will be based on a percentage of the total contract amount.
The bond assures the owner that the golf course builder will
perform the work for the contracted amount and per the terms
of the agreement.
[ Back ]
Back
to Previous
 ©2008 American Society of Golf Course Architects. All Rights Reserved.
Privacy Policy
|